Collaborative ConMon¶
Collaborative Continuous Monitoring Balance Improvement Release
This entire section and set of requirements does not apply to cloud service providers who have met all of the requirements for adopting the optional Collaborative Continuous Monitoring Balance Improvement Release.
The FedRAMP High, Moderate and Low baselines require CSPs to develop a ConMon strategy that complies with the requirements defined in CA-7, Security Assessment and Authorization | Continuous Monitoring.
FedRAMP does not currently have the capacity to actively monitor continuous monitoring for all Rev 5 FedRAMP Authorized services. Each agency that issues an ATO or Authorization to Use (ATU) for the CSO is responsible for performing oversight for their use of the system to ensure the security posture remains sufficient for its own use and supports an ongoing authorization.
For CSOs that have more than one active ATO/ATU on file with FedRAMP, CA-7 requires the CSP to implement a Collaborative ConMon approach. Collaborative ConMon benefits both agencies and CSPs:
-
Agency Benefits: Allows agencies to share responsibility for ConMon oversight and make better risk-based decisions through collaboration
-
CSP Benefits: Creates a central forum for addressing questions related to the CSP's ConMon activities, and achieving consensus on Deviation Requests (DRs), Significant Change Requests (SCRs) and the Annual Assessment (AA) - versus having to coordinate with each agency separately.
FedRAMP has worked with a number of CSPs to successfully implement Collaborative ConMon. In doing so, we have found there is no "one size fits all" approach. Therefore, this guide provides a framework that CSPs can leverage to develop their own Collaborative ConMon process. At a minimum, CSPs must include the following key elements in their Collaborative ConMon process.
Step 1: Develop Collaborative ConMon Draft Charter¶
The charter defines the process for conducting Collaborative ConMon. The draft charter should be shared with the member agencies ahead of the inaugural Collaborative ConMon meeting (see Step 2) for review and feedback. At a minimum, the charter should include the following sections, but CSPs and agencies are free to include additional sections or subsections to further define the Collaborative ConMon process:
Section 1: Collaboration Group Member Contact Information¶
In addition to the CSP, membership includes one or more security representative(s) from each agency. This may include the Authorizing Official (AO) at each agency; however, AOs typically delegate this responsibility to Information System Security Officers (ISSOs) on the Chief Information Officer's (CIO's)/Chief Information Security Officer's (CISO's) team. The Collaboration Group membership will change over time as new agency customers are onboarded or discontinue using the cloud service.
Points of Contact
You should already have direct points of contacts (POCs) at each agency as part of your Incident Response Plan, but the PMO recognizes that POC information may become outdated with employee turnover. Feel free to contact the PMO if you need help identifying security POCs at your member agencies.
Independent assessors are not typically included as members of the Collaboration Group unless you are using an assessor in a consulting role to perform ConMon activities. Assessors may be asked to attend Collaborative ConMon meetings on an ad hoc basis - for example, to brief the results of the Annual Assessment.
Section 2: Meeting Schedule¶
The PMO recommends holding a monthly, one-hour recurring Collaborative ConMon meeting. To ensure high participation, we recommend scheduling the recurring meeting on Tuesday, Wednesday, or Thursday and in the early afternoon (EST) to accommodate different time zones.
Optional Meetings
It may not be necessary for a CSP to meet each month with their agency customers if there are no substantial changes to the system or vulnerabilities identified. In such cases, the CSP can simply post their Continuous Monitoring reports to their respective repository and inform customers that the meeting is not being held that month.
Section 3: Meeting Agenda¶
A typical agenda for the monthly collaborative ConMon meeting includes:
-
Summary of monthly vulnerability scan results
-
Discussion of past due POA&Ms and any new POA&Ms that are dependent on a downstream vendor (i.e., Vendor Dependencies)
-
Open Deviations Requests (DRs) pending approval (Operational Requirements, Risk Adjustments, False Positives)
-
DRs newly approved
-
Significant Change Requests (SCRs) (planned changes, changes pending approval, status of implementation and testing)
-
Annual Assessment (scope of upcoming assessment, brief out assessment results)
-
Status of Incident Handling/Response, Cybersecurity and Infrastructure Security Agency (CISA) Emergency Directive, etc. (if applicable)
-
Agency-specific reporting requirements (if applicable)
-
Question & Answer (Q&A)
A good way to disseminate this information is in a summary report that agency representatives can use to brief their respective AOs on the security posture of the cloud offering.
Focused POA&M Discussions
It is not practical to cover every POA&M item, particularly those you intend to remediate within the FedRAMP-prescribed timeframes. The focus of the POA&M discussion should be the status of any past due POA&Ms, Vendor Dependencies, and Deviation Requests - most importantly, any areas that require risk acceptance.
Be sure to differentiate between changes that impact all agency customers versus a specific agency. For example:
-
A Low->Moderate or Moderate->High "uplift" is considered a significant change. Oftentimes, uplifts are requested by a single agency with a use case at the higher impact level. In this scenario, all agency customers should be made aware of the change, but the requesting agency should take the lead on reviewing and approving the SCR, reviewing the assessment results, and issuing an ATO at the higher impact level.
-
From time to time, CSPs choose to add services or features to the authorization boundary through the significant change process. This may be done at the request of one or more existing agency customers OR as an effort to expand the CSP's offering to attract new customers. If the latter, CSPs should not assume that existing agency customers will approve the addition of services/features. This is something that needs to receive buy-in from existing agency customers along with a commitment to review and approve the SCR, review the assessment results and issue an updated ATO that covers the expanded offering. Otherwise, the CSP will be required to find an agency willing to review the SCR and issue an ATO that covers the expanded offering.
Section 4: ConMon Deliverables¶
The PMO recommends uploading the monthly ConMon deliverables (summary report, vulnerability scan files, updated POA&M and Inventory, DRs, SCRs) on the same day each month and then hold the recurring meeting a week later. This will give each agency representative time to review the deliverables and come to the meeting ready with questions and recommendations for DR/SCR approvals.
Section 5: Decision-Making Authorities¶
Determining how decisions are made, and by whom, is a critical part of the Collaborative ConMon process. While it's important to give each agency a voice, it is not always practical or in the best interest of security to seek unanimous agreement - particularly if the issue at hand only affects a single agency. Most CSPs that have successfully implemented Collaborative ConMon have used one of two approaches (or some combination) to decision making.
Voting Members: During the inaugural Collaborative ConMon meeting, the collaboration group grants certain members decision-making authority for DRs, SCRs, or any other area that requires agency approval. Oftentimes, agency representatives will volunteer to take on this responsibility. Depending on the number of agency customers, the PMO recommends at least two (2) or more voting members share this responsibility.
Comment Period: Some collaboration groups have agreed to a "comment period" approach, whereby all group members are allowed an agreed upon period of time to raise questions, concerns or objections. If there are no objections when the time period ends, the matter is considered approved. The PMO recommends giving group members two weeks. For any group members that were unable to attend the monthly meeting, two weeks will allow those members to review the relevant documentation. This approach typically works as follows:
-
The CSP makes information (e.g., DR, SCR, etc.) available via the FedRAMP secure repository at least one week prior to the monthly Collaborative ConMon meeting and then notifies all group members.
-
During the monthly Collaborative ConMon meeting, the CSP briefs all group members on DR, SCR, etc. and holds room for Q&A.
-
After the monthly meeting, the CSP sends a follow up email that summarizes the discussion topics and reminds group members of the window of time to ask any follow up questions. After the defined Q&A period has ended, the CSP sends a follow-up email, informing group members that no objections were raised; therefore, the DR, SCR, etc. is considered approved.
Section 6: Agency-specific ConMon requirements¶
The charter should identify additional ConMon requirements that the member agencies need to meet their own agency-specific reporting requirements. Agency-specific requirements above and beyond the FedRAMP baselines should be documented in the contract and/or ATO letter.
Section 7: ConMon Performance Management¶
While it is ultimately up to each agency Authorizing Official to maintain or revoke an ATO, this section can be used by the collaboration group to define performance triggers and associated escalation levels (for example, Corrective Action Plan "In Remediation" status) when the CSP fails to comply with FedRAMP's continuous monitoring requirements or the agreed upon charter. The PMO recommends using the process defined in the Performance Management section of this playbook as the basis for this section.
Step 2: Hold Inaugural Collaborative ConMon Meeting¶
The goal of the inaugural Collaborative ConMon meeting is to introduce collaboration group members and achieve consensus on the draft charter. Keep in mind that agency representatives may have different opinions on the scope and structure of Collaborative ConMon. The PMO has found that most agencies are agreeable to holding monthly recurring meetings that cover the typical agenda described above. In addition, most agencies are agreeable to some form of the decision-making approaches described above. However, keep in mind that you may have to go through a couple iterations before the charter is finalized.
Step 3: Finalize Collaborative ConMon Charter¶
Once feedback from agency representatives has been received and incorporated into the draft charter, upload the final Collaborative ConMon Charter to the top-level ConMon folder in your secure repository and notify the collaboration group. Remember, as agency representatives join or leave the collaboration group, the charter should be updated to reflect the current member contact information. Maintaining an updated list of agency POCs is critical for effective communication in the event of a security incident, emergency directive, etc.
Step 4: Hold Monthly Recurring Collaborative ConMon Meetings¶
Now that you have identified collaboration group members and achieved consensus on the Collaborative ConMon Charter, you are ready to hold monthly recurring Collaborative ConMon meetings. Here are some tips for ensuring a smooth Collaborative ConMon process:
-
Upload deliverables to the secure repository at least one week prior to the meeting and remind the collaboration group to review the information prior to the meeting, especially if there are new areas that require discussion and approval, such as DRs and SCRs. Be sure to provide a link to the secure repository in the email notification.
-
Follow the typical agenda described above, but feel free to adjust it as needed. For example, you may use the meeting time to brief the results of the annual assessment (AA) or testing associated with a significant change. Be sure to invite the assessor to these types of meetings.
-
When you receive a new Agency ATO, forward it to the PMO at ato-letter@fedramp.gov and then invite the Agency AO to the monthly Collaborative ConMon meetings. Be sure to email the AO, explaining the meeting purpose and goals. The AO may choose to delegate this responsibility to members of the CIO/CISO team.
-
As collaboration group members join/leave the group, update the charter and monthly meeting invite. Keep in mind, as new agency representatives join the group, they may have different opinions about the scope and structure of the Collaborative ConMon process you have defined. Be open, flexible, and willing to make adjustments.
-
With enough notice, the PMO can attend monthly Collaborative ConMon meetings on an as-needed basis to provide guidance.